Disclaimer: This is based on conversations, anecdotal evidence and personal opinion. This is not backed by statistical evidence. But neither is the cargo cult around estimations (to my knowledge). š¤·š»āāļø
PM: How long will this take?
Me: I donāt know.
PM: We need to tell the business a date so they can make a decision.
Me: Yes, I understand where you are coming from, itās our job to enable non-technical business stakeholders to make decisions. However we donāt know what to build, so we cannot give them any dates.
PM: But they want [feature X].
Me: Sure, thatās what they ask for. But what are the business problems we are solving? Where is the value? Which scenarios will we support? And why?
PM: Ok, Iāll clarify and get back at youā¦ [walks away disappointed]
We donāt understand what business problem we are solving yet, so we
canāt estimate anything. Itās super common for business stakeholders or
users to ask for solutions instead of describing the problem they have.
Problem solved š.
PM: So we clarified with the business, they want to solve [problem] and I thought about solving it with [revised feature]. What do you think?
Me: Yeah sounds good. Itās technically feasible, I have a high level idea of how we can do this with our team. We can start working on it - you make the call.
PM: Wait a second - I need a date. How long will this take?
Me: I donāt know.
PM: But you know what we want to build, right? What else do you need to estimate the delivery date?
Me: Well truth isā¦.
The hard, honest truth is: Nobody knows.
At this point many people throw up their hands in despair and argue ābut we have all these estimation techniques, with numbers, discussions and processes! Our tools have these input fields for estimated effort and actual effort! We calculate velocity after every iteration!ā. Itās true we have all that and we do all those things. Still: nobody knows! Let me unpack what I mean by that.
Estimates are relative
We are bad at predicting the exact effort a feature will take in terms of hours and days. This stems from the inherent uncertainty: weāre doing something new, we donāt know all the minute details of the business problem and technical solution yet. More importantly we donāt know what we donāt know, this is something we cannot change. There are always unknown unknowns.Another reason why exact predictions are near impossible is that developers donāt know how much time they actually have available. Thereās 8 hours in a work day - but those are chopped up by meeting, interrupted by instant messages, eaten up by asynchronous communication and busy work. A developer may have 6 productive hours on a good day, but only 2 hours on a bad one. And that is completely out of the individualās control - āHey letās set up a sync up meetingā - said no developer, ever. Another, more subtle effect is that we all do creative work, which best in bursts of uninterrupted focus time. A 30 minute meeting in the middle of the morning chops the potential flow time from 4 hours into 2 hours. So on paper a creative worker may have 7 hours of time in the work day, but that is chopped up into 2 hours (or less) chunks which inherently limits productivity of creative work.Lastly we tend to forget to include everything in the estimation. Does the number include: automated tests? Code review? Discussions during development? Debugging the build script because suddenly everything broke? Having a 2 hour discussion with the product manager to finally figure out that you use the same words with different meanings? The potentially multiple round trips between QA & DEV?Long story short: exact, absolute effort estimates donāt exist. if you disagree - go home youāre drunk! (Actually stay, finish reading and then send me your counter arguments)However there is one thing of estimations that developers are really good at: Comparing effort. Allow me to illustrate:Me: How long will it take to add this dynamic marketing banner [that we just discussed for 10 minutes]?I bet youāve hadćthis conversation before (or at least overheard it). In my experience developers (designers in general) are pretty good at relative estimates. Yes there are still unknown unknowns, thatās where buffer/slack comes in. But all the stuff we tend to forget - the long list above - those are accounted for by giving estimations relative to past effort.This still does not give you an exact dates however, becauseā¦
Developer: No idea!
Me: Will it take longer than adding button that exports the report as a PDF?
Developer: Ohhhh no, that was way more complex. This is way smaller, maybe half of it. But donāt hold me to that!
Me: Donāt worry, I wonāt. How about this: Will it take longer than adding the dark theme to our application?
Developer: Hmmmā¦ itās kinda similar, maybe a little longer because of [technical reason X], but otherwise itās almost the same. Maybe 25% more work Iād say.
Estimates are distributions
Wait, what?Iām talking about probability distributions, something like a bell curve (= normal distribution). Now this is not my original insight, told me this. Itās probably not his original insight as well - but thatās not the point. The point is: estimates are distributions. In other words: the number a developer gives you carries a probability, donāt take it at face value. Try to figure out how likely it is.PM: How long will it take to build this dynamic banner?Neither of them is right. Because nobody knows. They both gave numbers, both numbers have a probability, maybe itās 25% chance that itāll take 2 days and 45% itāll take 6 days (and 30% for some other values). Again we donāt know. However being aware that every estimate is a distribution, rather than a number, enables us to understand it better. We can probe for the mean value and the deviation/variance of the distribution (how far the actual time strays from the mean).
Dev 1: Hmmmā¦ I think I could do it in 2 days
Dev 2: Really? I was thinking more likeā¦ 6 days?
[discussion ensues]
PM: So we have 2 days and 6 days. Both are possible, but let me ask you this: Do you think it could take 20 days?Now you have more data points, you know it will definitely be between 1.5-10 days. Itās still an estimate, nobody knows, but it is very likely that youāre team finishes in that time frame. More likely than the āletās average estimates (2 + 6) / 2 = 4 daysā approach anyways.
Dev 1 & Dev 2 (in unison): NO WAY!
PM: Okay, letās imagine everything goes wrong, and then some more. What is the very worst case?
Dev 2: Iād say 10 days.
Dev 1: Yeah that is possible.
PM: Ok understood. How about the very best case, everything goes perfectly and you flow for 8 hours straight?
Dev 1: Best case is 1 and a half days
Dev 2: Itās a bit of a stretch but maybeā¦
Estimates are proxies
Estimates and estimate derived metrics make for horrible KPIs. Calculating velocity and comparing teams based on that creates horrible incentives. Once a team learns that high velocity is good they will inflate estimates - be it story points or absolute time.āCourse correct and reward accurate estimates!ā the ambitious young middle manager might exclaim. What are the incentives now? Spending more time planning and estimating will produce more accurate predictions. Still nobody knows, so āmore accurateā only means lower variance of the distribution. Once a team learns that they will spend more time planning & estimating, less time creating. How about 2 days of planning a week? Sounds pretty unproductive, right? But that what our poor middle manager incentivizes.Estimates donāt tell you how productive a team is. The hard truth is that. Some people try to anyways and use some sort of velocity or estimation quality metric as a proxy. And that may make sense for some cases. But estimates as metrics are always only proxies for what you are actually interested in (time to market, business continuity, predictability etc.). Proxies donāt have value in and of themselves. The absolute values of a proxy usually does not matter, trends (sometimes) do. For example test coverage is a proxy for quality, but a value of 60% does not matter. What matters if your test coverage goes up or down. That tells you something is happening in the team, it triggers you to look into it. So velocity up or down? Something to look into, not telling if the team is doing well or not.In one sentence: Estimates are made up, don't trust them, don't spend a lot of time on them, instead pipeline work and monitor outcome.